Implementation Schedule |
|
|
The deployment of the wireless network core infrastructure and one half of the expected clients will occur in two phases over an eighteen-month period. The first phase of the rollout will entail hiring a Project Director and then the selection of a third party contractor for the network design, spectrum analysis survey, and wireless WAN installation. The chart below highlights the milestones associated with the rollout and reflects our intent to begin service as quickly as possible to the primary anchor tenants. Three Internet Fee Zones will also be created early on to help create demand for broadband. The Phase 1 objective is to provide service to county government and school system locations. Phase 2 will provide service to the maximum number of businesses and residential customers in each county in order to provide revenue to reach operational self-sufficiency. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|